What follows is our "Proposed" building schedule:
Items in RED have been completed.

Sept 8 & 9 ... Dig laterals
Sept 10 ... Dig basement
Sept 16 ... Form & pour footers
Sept 17 & 18 ... Form & pour walls
Sept 17 & 18 ... Run storm collection pipes, dig sumps
*Rough plumbing, pour basement floor
Sept 26 ... Decking
Oct 4 ... Receive walls from CrossRoads mission Sunday 3:30 PM
Oct 10 ... *BLITZ DAY
Oct 17 ... Finish roof decking & windows
Oct 24, 31 ... Roofing, Finish framing,Doors, Continue Siding
*Rough wiring, Plumbing, HVAC inspections
Nov 7 ...  No work
Nov 14 ...  Insulation &
*Insulation inspection, Continue HVAC& *Final grade, pour drive and walks
Nov 21 ... Hang Drywall, Paint trim,
Nov 28 ... No Work ... drywaller is finishing
Dec 5 ... Start painting
Dec 12 ... Painting
Dec 17... Hang doors, trim, porch, cabinets
Jan 9th ... counter tops, linen closet shelving, clothes closet
shelving, dryer vent, basement hand rail, leveler applied to dining
room in preparation for laminate floor, install baseboard, fill nail
holes and touch up paint.
Jan 16th ... touch up paint

DEDICATION SCHEDULED FOR SUNDAY, JAN 31st AT 1:00PM

???  Floor coverings
???   Home Dedication

Please understand ... putting a build
schedule together is like herding cats:  it
doesn't always go as planned.
There are many variables that will change a schedule....weather, suppliers,
Holidays, inspections etc.
 
327 E. Friendship St, Medina

Saturday, Jan 30TH

NO WORK SATURDAY.  SEE YOU AT THE DEDICATION AT
1:00 PM SUNDAY, JAN 31