| Current Projects ... 327 E. Friendship St., Medina |
| We are looking for available lots in Medina County to build on. If you know of any please call. |


| What follows is our "Proposed" building schedule: Items in RED have been completed. Sept 8 & 9 ... Dig laterals Sept 10 ... Dig basement Sept 16 ... Form & pour footers Sept 17 & 18 ... Form & pour walls Sept 17 & 18 ... Run storm collection pipes, dig sumps *Rough plumbing, pour basement floor Sept 26 ... Decking Oct 4 ... Receive walls from CrossRoads mission Sunday 3:30 PM Oct 10 ... *BLITZ DAY Oct 17 ... Finish roof decking & windows Oct 24, 31 ... Roofing, Finish framing,Doors, Continue Siding *Rough wiring, Plumbing, HVAC inspections Nov 7 ... No work Nov 14 ... Insulation & *Insulation inspection, Continue HVAC& *Final grade, pour drive and walks Nov 21 ... Hang Drywall, Paint trim, Nov 28 ... No Work ... drywaller is finishing Dec 5 ... Start painting Dec 12 ... Painting Dec 17... Hang doors, trim, porch, cabinets Jan 9th ... counter tops, linen closet shelving, clothes closet shelving, dryer vent, basement hand rail, leveler applied to dining room in preparation for laminate floor, install baseboard, fill nail holes and touch up paint. Jan 16th ... touch up paint DEDICATION SCHEDULED FOR SUNDAY, JAN 31st AT 1:00PM ??? Floor coverings ??? Home Dedication |
Please understand ... putting a build schedule together is like herding cats: it doesn't always go as planned. There are many variables that will change a schedule....weather, suppliers, Holidays, inspections etc. |
| 327 E. Friendship St, Medina Saturday, Jan 30TH NO WORK SATURDAY. SEE YOU AT THE DEDICATION AT 1:00 PM SUNDAY, JAN 31 |